Case Study 4: Major Urban Waste Water Treatment Works
Clayton Reference CP 000097
Site A major urban waste water treatment works.  
Objective To provide a new chemical dosing system, based on client
design parameters.
Solution We designed (wholly in house) a self-contained dosing system incorporating variable speed dosing pumps suitable for the highly aggressive
dosed medium and all manufactured using fusion welded  pipework housed
in a GRP enclosure.
Notes Contract was undertaken on an open book basis.  
Customer information available for reference.
 
Group Companies Group Information Contact & Find Us Group Services Group Services
CASE STUDIES
1: Main Water Filter
for Holiday Town 2: Critical Raw Water
Pumping Station 3: Offshore Water
Treatment Works 4: Major Urban Waste
Water Treatment Works 5: Major Screened Waste
Water Pumping Station 6: Sewers for Adoption
Pumping Station 7: 1960s Pumping
Station 8: Rapid Gravity Filters
for Major Works 9: Bus Station
Development 10: Water Works on the Mersey Ship Canal 11: Potable Water
Booster Station