Case Study 9: Bus Station Development
Clayton Reference CL006843
Site A CSO located under a new bus station development.
Objective To install a new hydraulic operated CSO screen complete with a free issue control panel.
Solution We undertook the design, specification and liaison between ourselves, the screen manufacturer and the control panel manufacturer. The system was a key element of the overall development, and was installed, cabled and commissioned by ourselves to meet the client’s program.
Notes The installation was completed within program comprising of two elements, which included temporary and permanent works to facilitate the civil construction.
Customer information available for reference.
Group Companies Group Information Contact & Find Us Group Services Group Services
CASE STUDIES
1: Main Water Filter
for Holiday Town 2: Critical Raw Water
Pumping Station 3: Offshore Water
Treatment Works 4: Major Urban Waste
Water Treatment Works 5: Major Screened Waste
Water Pumping Station 6: Sewers for Adoption
Pumping Station 7: 1960s Pumping
Station 8: Rapid Gravity Filters
for Major Works 9: Bus Station
Development 10: Water Works on the Mersey Ship Canal 11: Potable Water
Booster Station